CONSTRUCTION STATUS:
Magnolia Rd. (Cullen Pkwy. to Harkey Rd.): Storm drainage and paving are 70%
complete, sanitary sewer is 40% complete, water line is 65% complete, and bridge
work is 41% complete.
Southfork Dr. (Morgan Rd. to Cullen Pkwy.): Paving is 95% complete, and bridge work is
95% complete, landscaping is 5% complete.
Cullen Parkway work is beginning with the scheduled traffic switch to temporary
pavement on May 14th. This work has a 6-month milestone timeframe with liquidated
damages if exceeded, work started April 13th. _________________ Rob Nunez |
|